One month after the Japanese tsunami, the world’s biggest reserve of plutonium waste is reaching crisis point. It was meant to be reprocessed and sold – but now no nation will take it. So where is this vast stockpile? Not Fukushima, but Sellafield, Cumbria

it goes on to say

“The existing Sellafield Mox Plant, opened in 2002, has cost more than £1.3bn to date yet has produced just 13.8 tons of Mox fuel in nine years compared to an expected output of 120 tons per year. A leaked cable from the US embassy in London said Sellafield’s Mox plant was a white elephant costing about £90m a year and considered, privately, by the UK Government as “[one of] the most embarrassing failures in British industrial history”.